IPO Research · Deep Dive

SB Energy

SoftBank's AI data center developer has a public S-1 on file for Nasdaq ticker SBE: $439 billion of contracted backlog, a $176 billion bill to build it, and $213.5 million of revenue in 2025.

QuantLogix Research November 28, 2026 ~14 min read Coverage: SFTBY · NVDA · CRWV · VST · CEG
Executive Thesis

SB Energy, Inc. is the rare 2027 IPO candidate whose prospectus is already public. It filed a Form S-1 on September 1, 2026, planned a roadshow for the week of September 21, then held the deal when investors balked at a valuation of about $50 billion (IFR). Amendment No. 3, filed November 19, 2026, adds third-quarter financials and confirms the ticker SBE on the Nasdaq Global Select Market and Nasdaq Texas, but the price range is still blank. The equity story is a contracted one: $439 billion of backlog, almost all of it from leases with two related parties, SoftBank and OpenAI, with OpenAI's 8.0 GW Ohio campus backed by a $105 billion NVIDIA residual value guaranty. The operating story is still ahead of it: no data center capacity is in operation, revenue was $213.5 million in 2025 and came almost entirely from solar and storage, and delivering the backlog takes an estimated $176 billion of capex over about six years. The IPO asks public investors to pay for leases that start paying out from 2028.

The Numbers at a Glance

Contracted Backlog
$439B
$430B data centers · $10B power
Backlog-Associated Capex
$176B
Over about six years · cash basis
2025 Revenue
$213.5M
Net loss $738.0M (incl. $674.1M stock comp)
Reported Valuation Target
~$50B
Reuters, May 2026 · not in the filing

Backlog, capex, revenue and loss figures are from SB Energy's S-1/A No. 3 (November 19, 2026). The valuation target is press reporting (Reuters in May 2026; IFR in September 2026) and does not appear in the filing, which leaves the price range and share count blank.

1 · Business Overview

A SoftBank solar developer turned gigawatt-scale data center builder

ItemDetail
RegistrantSB Energy, Inc. · Texas corporation (converted from Delaware August 28, 2026) · SEC CIK 0002133037 · formerly SE Global Holdings
Headquarters3 Lagoon Drive, Suite 280, Redwood City, California
Founded2019 by SoftBank Group, as a power infrastructure business
LeadershipCo-Chief Executive Officers Rich Hossfeld and Abhijeet Sathe
People251 full-time employees and 108 contractors (September 30, 2026)
SegmentsData centers (DC) and solar, storage and power (SP)
Data center portfolio8.8 GW-IT under signed leases: 0.8 GW-IT under construction (Cosmos, Milam County Buildings 1 and 2) and the 8.0 GW-IT PORTS-Pike Technology Campus in Ohio, contracted but not yet under construction
Power portfolio5.5 GWac operating, under construction or contracted: about 2.2 GWac of solar and battery storage in service, about 2.5 GWac in construction, 0.8 GWac more contracted
Track record4.7 GWac of solar and storage developed, financed and started since 2019; 24 customers; 37 project financings; acquired data center builder Studio 151 in 2025
Strategic holdersSoftBank (controlling shareholder and tenant) · OpenAI (tenant and warrant holder) · NVIDIA (residual value guarantor and future Class N holder)

SB Energy began as SoftBank's renewable power developer and pivoted in 2025 toward AI data centers, keeping the power business as its source of revenue today. Its pitch is "power-first": it builds the generation and grid connection alongside the data halls, so customers get capacity sooner. The prospectus calls time to energization "the defining variable in data center development." Three campuses carry signed leases. Cosmos in Travis County, Texas is a roughly 50 MW research campus leased to a SoftBank affiliate for 15 years. Milam County, Texas has two buildings of about 308 MW and 445 MW leased to an OpenAI affiliate for 15 years. PORTS-Pike in Pike County, Ohio, on a former Department of Energy uranium-enrichment site, is planned as 17 buildings of about 472 MW each under separate 20-year leases to OpenAI, supported by about 10 GW of grid power and an initial 9.2 GW of new gas-fired generation.

2 · What EDGAR Shows

A public S-1, three amendments, and a roadshow that has not started

Filing status here is read directly from SEC EDGAR. SB Energy skipped the quiet route Wonder and OpenAI took: it filed in public, so its financial statements, risk factors and contracts are already readable. What is missing is the deal itself: the price range, the share count and therefore the valuation.

DateEventWhat changed
August 17, 2026NVIDIA prepaid forward and PORTS-Pike guarantyNVIDIA prepays $1.5B for Class N shares at 90% of the IPO price; announces the guaranty for the Ohio campus
September 1, 2026Public Form S-1First public prospectus (Registration No. 333-298675)
September 4, 2026S-1/A No. 1Exhibits only
September 21, 2026S-1/A No. 2 · planned roadshow weekDiscloses the NVIDIA prepaid forward; banks hold the launch over valuation (IFR)
October 22, 2026Press reportThe Information: SB Energy weighing a December 2026 or 2027 listing
November 19, 2026S-1/A No. 3Adds results for the nine months to September 30, 2026; ticker SBE on Nasdaq Global Select and Nasdaq Texas; price range still blank

The syndicate is one of the largest on file: 21 underwriters, with J.P. Morgan, Goldman Sachs and Morgan Stanley as representatives and Citigroup and Mizuho among the lead books (IFR). The usual next step is a price-range amendment followed by a roadshow of one to two weeks. A practical deadline sits behind the timing: the filing's latest financial statements are as of September 30, 2026, and SEC staleness rules generally require newer audited figures for an IPO priced roughly 135 days after that date, which falls in mid-February 2027.

3 · The $439 Billion Backlog

Two related-party tenants, one Ohio campus, and a guaranty doing the heavy lifting

SB Energy defines backlog as revenue still to be recognized under binding contracts. It excludes merchant power sales and uncontracted renewals. As of the prospectus date it totals about $439 billion: $430 billion in the data center segment and $10 billion in power. The weighted average remaining contract length is 19.6 years for data centers and 16.5 years for power. Two facts dominate the number:

CampusTenantCritical IT capacityLeaseStatus
Cosmos Research Campus, Travis County, TexasSoftBank affiliate~50 MW15 years · ~$2.5B aggregate rent · SoftBank guaranty ~$2.9BUnder construction · rent starts the earlier of December 11, 2026 or ready-for-service
Milam County Buildings 1 and 2, TexasOpenAI affiliate~308 MW + ~445 MW15 years each · two 10-year extensions · yield-on-cost rent with escalatorUnder construction
PORTS-Pike Technology Campus, Pike County, OhioOpenAI~8.0 GW (17 × ~472 MW)17 separate 20-year triple-net leasesContracted, not yet under construction · phased delivery reported from 2028

First, every signed data center lease is with SoftBank or OpenAI; the prospectus says there are no unaffiliated data center tenants, and talks with other hyperscalers have produced no definitive agreements. Second, PORTS-Pike is all of the contracted-but-not-started capacity and "a substantial majority" of data center backlog. Because OpenAI "is not currently an investment-grade tenant," the campus's financeability rests on NVIDIA's residual value guaranty. That guaranty covers only the first 4.25 GW-IT of the 8.0 GW-IT, is capped at $105 billion, declines over each 20-year lease, pays only on tenant insolvency or an uncured monetary default, and ends automatically if OpenAI Group PBC earns a designated credit rating. The remaining 3.78 GW-IT has only an option for NVIDIA to guarantee, at its sole discretion.

Backlog, the capex to deliver it, and last year's revenue
USD billions · three cited figures from S-1/A No. 3 · linear scale, so 2025 revenue barely registers
Contracted backlog Backlog-associated capex 2025 revenue $439B $176B · ~6 years $0.21B ($213.5M)

4 · The Financial Picture

A small power business carrying a very large construction program

Total revenue by reported period
USD millions · three reported periods · 2026 covers nine months only · includes realized and unrealized swap gains
$250M $187.5M $125M $62.5M $0 $232.2M $213.5M $177.1M 2024 2025 Nine months to September 2026
Line202420259 months 2026
Total revenue$232.2M$213.5M$177.1M
of which revenue from contracts with customers$100.6M$143.0M$109.8M
of which unrealized change in fair value of power swaps$119.3M$63.3M$59.0M
Net income (loss) attributable to SB Energy$106.1M−$738.0M−$1,913.7M
Stock-based compensation (non-cash)$140.3M$674.1M$593.6M
Warrant liability fair-value change (non-cash)——$1,202.8M
Net income (loss) excluding those non-cash items (company measure)$246.4M−$63.9M−$117.3M

Three things stand out. Revenue has not grown: it is still a solar and storage business, and a sizeable share of the top line is unrealized gains on power price swaps, not cash from customers. The headline losses are mostly non-cash: the $1.2 billion warrant charge in 2026 is the remeasurement of outstanding warrants to fair value (OpenAI and Ares hold the company's warrants), and stock compensation ran at $674.1 million in 2025. And the balance sheet is thin for the plan: at September 30, 2026 the company held $996.7 million of unrestricted cash, $1,155.6 million of restricted cash and $1.9 billion of undrawn committed credit, against $4.6 billion of debt, of which $1.2 billion is current. The largest near-term maturity is the Pelicans Jaw facility, about $874.8 million due by March 2027. Accumulated deficit reached $2.51 billion.

⚡ The Capex Arithmetic
$176 billion over six years against a $5–7 billion IPO

The prospectus estimates $176 billion of capex tied to contracted projects alone, about 31% in years 0–2, 41% in years 2–4 and 28% in years 4–6. That is roughly $55 billion in the first two years (QuantLogix arithmetic). The reported IPO raise of $5–7 billion (The Information) plus NVIDIA's $3.0 billion covers a small fraction; the rest has to come from project-level debt secured on the leases, which is why the NVIDIA guaranty and OpenAI's credit standing carry so much weight. The IPO is a down payment on the build, not its funding.

5 · Ownership and Capital Structure

A controlled company with two strategic side doors

HolderInstrumentTerms
SoftBank GroupCommon stock (controlling)Keeps voting control after the IPO; SB Energy will be a Nasdaq "controlled company" and intends to use the governance exemptions. Post-IPO percentages are blank in the filing
NVIDIAClass N common stock (non-voting)$1.5B prepaid forward (August 17, 2026) at 90% of the IPO price, plus a $1.5B concurrent private placement at the IPO price: $3.0B in total. The IPO is not conditioned on either
OpenAIWarrants3,991,809 warrants (amended and restated August 17, 2026). 1,737,867 are net-exercised automatically at the IPO; 2,253,942 stay unvested
Ares ManagementPreferred equity and warrantsPreferred equity redeemed in full and warrants cash net-settled, expected before or substantially concurrently with the offering
IPO investorsCommon stockUp to 5% reserved for a directed share program; 180-day lock-up for existing holders

The structure is close to Anthropic's: Anthropic sold $26 billion of non-voting Class N stock to strategic partners, NVIDIA among them, alongside its November 2026 IPO. Here the strategic partners are also the tenants and the guarantor. The prospectus is direct that a dispute with SoftBank or OpenAI "could be complicated by SoftBank's controlling interest," and that the board may face conflicts enforcing rights against a related-party tenant.

6 · The Valuation Gap

$50 billion asked, investors bidding lower, and no operating data center yet

No private round has priced the company; the only marks are reported IPO targets. Reuters reported in May 2026 that SB Energy was aiming for about $50 billion. IFR reported in September that it hoped to raise at least $5 billion at that valuation but that premarketing interest came in below it ("the valuation gap is a big issue," a banker told IFR). The Information reported in October that banks had put the value at about $60 billion and that investors found it hard to accept because the valuation rests on future leases.

YardstickAt $50BBasis
Price to 2025 revenue~234×$50B ÷ $213.5M (QuantLogix arithmetic)
Price to backlog~0.11×$50B ÷ $439B, before $176B of capex to earn it
Backlog net of capex~$263B$439B − $176B, undiscounted, before interest, operating costs and taxes

Neither multiple is a fair valuation on its own. The revenue multiple ignores the leases; the backlog multiple ignores that most of the rent arrives over 20-year terms starting in 2028 and needs the capex first. The right public-market frame is a discounted lease book with construction risk, which is how investors price listed data center developers, and the market for those names soured during the autumn: The Information tied SB Energy's delay to stress in CoreWeave's bonds, and Australian developer Firmus withdrew its IPO in October.

"SB Energy is selling a 20-year lease book whose largest tenant is not investment-grade, whose largest asset has not broken ground, and whose controlling shareholder is also its landlord's tenant."

7 · IPO Timing: December 2026 or 2027?

The amendment keeps the option open; the tape decides

SignalReads as
S-1/A No. 3 with September 30 financials (November 19, 2026)Supports The company keeps the filing current rather than letting it lapse
Price range and share count still blankNeutral No launch yet; a range amendment comes before any roadshow
Anthropic priced at $83 on November 18, then closed below $83 on November 24 (CNBC)Against SB Energy's executives were reported to be watching Anthropic's trading before deciding on December
First data center rent (Cosmos) expected in the fourth quarter of 2026Supports A first lease in service would give the roadshow an operating proof point
Financial statements go stale around mid-February 2027Neutral A slip past that point means waiting for audited 2025-26 year-end figures

QuantLogix's base case is a first-quarter 2027 listing, after Cosmos starts paying rent and once the AI listings that came before it have settled. A December 2026 launch remains possible if Anthropic recovers. The deal most likely prices below the $50 billion target; NVIDIA's purchase at the IPO price and its 10%-discount prepaid forward show where strategic money is already committed.

8 · How It Compares

Part data center developer, part power producer, part OpenAI credit

CompanyTickerOverlap with SB Energy
CoreWeaveCRWVAI capacity sold to a few large labs, OpenAI among them; its bond spreads were the stress signal cited in SB Energy's delay
Vistra · ConstellationVST · CEGListed power producers priced on contracted supply to data centers
NextEra EnergyNEEThe largest listed U.S. solar and storage developer: the closest match to SB Energy's revenue today
Equinix · Digital RealtyEQIX · DLRListed data center landlords with diversified tenant bases: the profile SB Energy lacks, with two related-party tenants
AnthropicANTThe template for strategic Class N placements; not a business comp

No listed company combines a 20-year lease book this concentrated with a construction program this large. Expect the roadshow to pitch SB Energy as a contracted infrastructure yield story and the market to test it as an OpenAI credit story.

9 · Key Risks

What public-market diligence will price in

RiskSeverityDetail
Tenant concentration and creditHighAll signed data center leases are with SoftBank or OpenAI affiliates; OpenAI is not investment-grade
Guaranty limitsHighNVIDIA's guaranty covers 4.25 of 8.0 GW-IT at PORTS-Pike, is capped at $105B, declines over time and can terminate
Funding the buildHigh$176B of backlog-associated capex; $996.7M unrestricted cash and $4.6B of debt at September 30, 2026
Execution at PORTS-PikeHigh17 buildings and 9.2 GW of new gas generation on a former DOE site; federal permitting still in progress
Related-party governanceMediumSoftBank controls the board and is a tenant; controlled-company exemptions apply
Revenue qualityMediumUnrealized swap gains were $63.3M of 2025's $213.5M revenue
Community and political riskMediumIFR reported investor caution over the data center backlash heading into the November 2026 midterms
IPO windowMediumDelayed once on valuation; Anthropic's post-IPO trading is the reported swing factor

10 · How to Get Exposure Today

The parent, the guarantor, and the IPO itself

VehicleTickerTypeExposure
SoftBank Group9984 (Tokyo) · SFTBYControlling shareholderThe direct look-through today, diluted by SoftBank's much larger OpenAI, Arm and Vision Fund positions. IFR reported SoftBank arranging a margin loan against part of its SB Energy stake
NVIDIANVDAStrategic investor and guarantor$3.0B of Class N stock at or below the IPO price, plus contingent exposure under the $105B guaranty; immaterial to NVIDIA's size
OpenAIPrivateTenant and warrant holderNo listed route; see the QuantLogix OpenAI deep dive
The IPOSBEDirectCommon stock once a price range is filed and the offering launches

Bottom Line

SB Energy offers the most transparent 2027 AI-infrastructure IPO on file: a public prospectus, a ticker, 21 banks and $3.0 billion of NVIDIA money committed. It also offers the most concentrated one: $439 billion of backlog that depends on two related parties, a $176 billion build that has not started at its largest site, and a business that made $213.5 million last year. The $50 billion target was too rich for investors in September; the deal now waits on Anthropic's trading and Cosmos's first rent check. The event that changes the analysis is the price-range amendment: it sets the valuation, SoftBank's retained stake and NVIDIA's share count in one page. Until then, SB Energy is a watchlist name for the first quarter of 2027.

Track SB Energy's filing from public S-1 to price range, alongside OpenAI, Anthropic and 2,800+ private companies, on QuantLogix's Private Companies dashboard.
Open the SB Energy profile →